4–20 mAalso: 4-20 mA, 4–20mA, current loop
A sensor sends a changing electrical current to represent a measurement. Usually 4 milliamps means the range's bottom and 20 its top.
On site A tank instrument sends a small current through its cable to report the water level.
Siemens Configure the analogue input's current range and scale its reading to engineering units.Rockwell Configure the analogue module's current range and scaling to match the transmitter.
Taught in: From milliamps to a number you can trust
Accumulatoralso: ACC, CV, accumulated value
The current total inside a timer or counter. It shows time passed or events counted, rather than the target.
On site A counter's current total reads two after two separate bottles arrive.
Siemens ET for elapsed timer time; CV for the counter value.Rockwell ACC for a timer or counter's accumulated value.
Taught in: Make time explicit
Acknowledgealso: Ack, acknowledgement, acknowledgment
Tell the system that the operator has noticed an alarm. This can silence a horn without fixing or clearing the problem.
On site An operator silences the high-level horn while investigating why the tank is filling.
Taught in: Acknowledge the horn, retain the alarm
Actuatoralso: final control device
The part that makes equipment move or change when commanded. It turns a control request into a physical action.
On site An air-powered actuator turns a tank valve open or closed.
Alarmalso: warning alarm
A warning that something needs attention. The programme decides when it appears, whether it stays and how it clears.
On site A mixing tank warns the operator when a valve fails to open in time.
Taught in: Separate request from evidence
Analoguealso: analog, analogue signal, analog signal
A measurement that can vary across a range, rather than only ON or OFF. Temperature and tank level are examples.
On site A level instrument reports how full a tank is throughout its filling cycle.
Taught in: Follow the signal
ANDalso: and operator
Both conditions must be true. Start AND Permit allows a request only when permission is also present.
On site A wash pump needs both an operator request and enough water in its supply tank.
Siemens AND in SCL, series contacts in LAD and & in FBD.Rockwell AND in ST, series instructions in Ladder and BAND in FBD.
Taught in: Build permission into the logic
AOIalso: Add-On Instruction, add on instruction
A reusable instruction an engineer defines for a repeated job. Each use needs separate storage when its machines must act independently.
On site A factory uses one tested pump instruction for several independent pumps.
Siemens A Siemens FB provides a comparable reuse pattern, with different interfaces and lifecycle rules.Rockwell A Logix Add-On Instruction definition is called with a backing instance tag.
Taught in: One definition, separate instances
Arrayalso: one-dimensional array
A collection of numbered values kept under one name. Each position holds the same kind of value.
On site A level filter keeps the last few measurements in a numbered collection.
Siemens ARRAY[0..7] OF REAL declares eight values in the supported SCL interface.Rockwell REAL[8] declares eight values, indexed 0 through 7, in Logix tags.
Taught in: Four values, one bounded loop
Assignmentalso: :=, assign
Writing a value into a named place. In text code, the name on the left receives the value calculated on the right.
On site PumpOn := Start makes the pump command follow the current Start request.
Siemens SCL uses :=; graphical MOVE boxes copy values.Rockwell ST uses :=; Ladder MOVE copies values (formerly MOV).
Taught in: Think in scans
At speedalso: at-speed, at reference, AtReference
A drive's report that the motor has reached the speed it was asked for. While the drive ramps, this signal is off.
On site A pump's ready lamp waits for its drive to report at speed.
Siemens SINAMICS drives report it in status word ZSW1.Rockwell PowerFlex add-on profiles report it as AtReference.
Taught in: Ask a drive, then check
BOOLalso: Boolean, Boolean value
A value with only two choices: TRUE or FALSE. It cannot hold a measured amount such as 42 litres.
On site A float switch gives an ON or OFF reading when water reaches it.
Siemens BOOL in block interfaces and PLC tags.Rockwell BOOL in controller/program tags.
Taught in: Know what a tag represents
CASEalso: CASE statement
Choose one section of code using a value, such as a state number. Only the matching section runs in that CASE call.
On site State 10 runs the batch; State 30 keeps the equipment stopped while held.
Siemens CASE ... OF ... END_CASE in SCL.Rockwell CASE ... OF ... END_CASE in ST.
Taught in: Write one phase as a state machine
Comparisonalso: compare
A test that compares two values and gives TRUE or FALSE. Level > 90 asks whether the level exceeds 90.
On site The controller compares the measured tank level with its filling limit.
Siemens SCL comparison operators; CMP boxes in graphical languages.Rockwell ST comparison operators; v38 Ladder uses LT/GT/EQ/NE/LE/GE.
Taught in: Build permission into the logic
Counteralso: event counter
An instruction that remembers how many events occurred. Counting an arrival once is different from adding one on every scan.
On site A drinks line stops after the third bottle passes the sensor.
Siemens CTU; SCL calls the declared IEC_COUNTER instance's CTU operation.Rockwell CTU in Ladder; CTUD with an FBD_COUNTER backing tag in ST.
Taught in: Count events, not scans
Deadbandalso: alarm deadband, alarm hysteresis
A gap between the point where an alarm comes on and the point where it goes off. It stops a rippling reading from flashing the alarm.
On site A high-level alarm comes on at 85 percent and clears only below 80 percent.
Siemens WinCC analogue alarms can add hysteresis; you can also write it in the programme.Rockwell The ALMA instruction and FactoryTalk alarms have a deadband setting.
Taught in: Give alarms a deadband
DINTalso: double integer
A whole-number type with a larger range than INT. It is useful for totals and numbered programme states.
On site A filling line keeps its accumulated bottle count in a DINT.
Siemens 32-bit signed DINT.Rockwell 32-bit signed DINT, also used for classic counter PRE/ACC.
Taught in: Know what a tag represents
Dutyalso: duty pump, lead pump
The equipment chosen to do the normal job first. Another unit may be available as a spare.
On site One water pump normally supplies the upper floors of a block of flats.
Taught in: One request, one eligible pump
Elapsed timealso: ET, timer elapsed
How much of a wait has passed so far. It is different from the target duration.
On site The operator checks how long the valve has been commanded open without confirming movement.
Siemens ET on the IEC timer instance.Rockwell ACC on the timer backing tag.
Taught in: Make time explicit
Engineering unitsalso: EU, engineering unit
The units people use for a measurement, such as percent, bar or degrees. Scaling turns raw input counts into them.
On site The tank screen shows the level in percent, not in input counts.
Siemens SCALE_X sets them with its MIN and MAX.Rockwell SCP calls them Scaled Min and Max; SCL calls them InEUMin and InEUMax.
Taught in: From milliamps to a number you can trust
Falling edgealso: negative edge, TRUE-to-FALSE
The moment a signal changes from TRUE to FALSE. A signal that was already FALSE has not just fallen.
On site A bottle clearing the sensor creates one falling edge.
Siemens F_TRIG in SCL; N contact or N_TRIG in LAD.Rockwell OSF in Ladder; this academy's ST exercise compares the current and previous input explicitly.
Taught in: Count events, not scans
FALSEalso: false value
A value meaning no, false or inactive. FALSE on Start means no start request is present.
On site A valve-open command becomes FALSE when the tank has enough water.
Taught in: Know what a tag represents
Faultalso: fault condition
A sign that something is not working as expected. Its effect on commands must be defined in the programme.
On site A failed duty pump makes the water system choose the spare pump.
Taught in: Build permission into the logic
Feedbackalso: actual-state feedback
A reading that reports what equipment actually did. A command to open a valve and proof that it opened are different things.
On site A valve's open switch confirms movement after the controller asks it to open.
Taught in: Separate request from evidence
Flow meteralso: flowmeter, flow transmitter
An instrument that measures liquid or gas passing through a pipe. Its reading can show whether a pump command actually produced flow.
On site A water-pump meter reports how many litres pass each second.
Taught in: Separate request from evidence
FORalso: FOR loop
Repeat code while a counting value moves from a chosen start to an end. Both ends are included in these languages.
On site FOR from zero to three visits all four stored readings.
Siemens FOR ... TO ... BY ... DO ... END_FOR in SCL.Rockwell FOR ... TO ... BY ... DO ... END_FOR in ST.
Taught in: Four values, one bounded loop
Function blockalso: FB
A reusable piece of programme with its own remembered values. Give each separate machine its own copy of that memory.
On site Two pumps use the same control design but keep separate start totals.
Siemens An FB definition is called with its own instance data.Rockwell An AOI provides reusable custom control logic; its instance tag holds data.
Taught in: One definition, separate instances
Function block diagramalso: FBD
A diagram language that connects the results of boxes to other boxes. Each connection carries a value used in a calculation or decision.
On site An engineer follows a tank measurement through scaling and level comparison boxes.
Siemens FBD networks use Siemens instruction boxes and parameter names.Rockwell FBD routines use Logix blocks, backing tags and their execution rules.
Taught in: Follow the signal
GRAPHalso: Siemens GRAPH
Siemens' language for describing a job as steps, conditions between steps and actions. It makes the order of a batch visible.
On site An engineer reads the Fill, Mix and Drain steps of a tank's batch programme.
Siemens GRAPH in TIA Portal.Rockwell The comparable sequence language is SFC; its execution settings differ.
Taught in: Describe a process in steps
HMIalso: Human-Machine Interface, operator panel
A screen where an operator sees readings and makes requests. It shows the programme's information but does not replace the controller.
On site A tank panel shows level and lets the operator request a batch start.
Siemens WinCC is a Siemens HMI software family.Rockwell PanelView terminals and FactoryTalk View are Rockwell HMI products.
Hysteresisalso: level band, two-threshold control
Using different points to start and stop an action. Between those points, keep the previous decision instead of switching repeatedly.
On site A tank pump starts below 30 percent and keeps filling until 70 percent.
Taught in: Control a band, not a point
Indexalso: array index
The whole number selecting one position in an array. You may use only positions inside the declared range.
On site Readings[0] selects the first stored measurement in a zero-based collection.
Taught in: Four values, one bounded loop
Inputalso: input signal
Information arriving at the controller, such as a button request or a measured water level.
On site A bottle sensor tells the controller when a bottle is under the nozzle.
Taught in: Know what a tag represents
Instancealso: instance data, backing tag
The separate storage used by one timer or reusable block. Sharing the design does not mean sharing every machine's remembered values.
On site The duty and spare pumps have separate memory even though they use the same control block.
Siemens Static timer instances; FB instances have instance data blocks or multi-instance storage.Rockwell Instruction backing tags and separate AOI instance tags.
Taught in: Make time explicit
INTalso: integer
A whole-number type that can hold positive or negative values. It cannot keep a fractional reading such as 41.5.
On site A small batch counter records three bottles as a whole number.
Siemens 16-bit signed INT; the supported IEC_COUNTER uses INT values.Rockwell 16-bit signed INT; Logix counter ACC is DINT.
Taught in: Know what a tag represents
Interlockalso: run inhibit
A condition that prevents or stops an action when another condition is unsuitable. Its exact rules belong in the programme.
On site A low-water switch stops a pump before it runs dry.
Taught in: Build permission into the logic
Ladderalso: LAD, LD, ladder logic, RLL
A diagram language using conditions and output instructions along paths. Read which conditions allow each path to reach its output.
On site An engineer checks both the Start path and the holding path before accepting a pump circuit.
Siemens LAD networks with contacts, coils and instruction boxes.Rockwell Ladder rungs using instructions such as XIC, XIO and OTE.
Taught in: Read a rung
Latchalso: latched command
A remembered ON value that stays on after the original request ends. Another instruction must deliberately turn it off.
On site A high-level alarm stays displayed until the water falls and the operator resets it.
Siemens S/R coils or explicit SCL assignments can store and clear a BOOL.Rockwell OTL/OTU instructions or explicit ST assignments can store and clear a BOOL.
Taught in: Read a rung
Level transmitteralso: level instrument
An instrument that reports how much liquid is in a vessel. Unlike a simple level switch, it can report a changing measurement.
On site A mixing-tank instrument sends its level reading to the controller.
Taught in: From milliamps to a number you can trust
Limit switchalso: position switch, open limit, closed limit
A switch that reports when equipment reaches a particular position. It gives an ON or OFF answer rather than a complete travel measurement.
On site A valve's open limit switch confirms that it reached its open position.
Taught in: Separate request from evidence
Loopalso: iteration
A section of code that repeats. A clear stopping rule keeps it from repeating forever.
On site The programme adds four meter readings by visiting each stored value once.
Siemens FOR loops are supported in this academy's SCL subset.Rockwell FOR loops are supported in this academy's ST subset.
Taught in: Four values, one bounded loop
Memberalso: structure member
One named value inside a group of values. A dot separates the group's name from the value's name.
On site Status.Level is the level value inside the Status group.
Siemens Local SCL example: #Status.Level.Rockwell ST example: Status.Level.
Taught in: Data is not executable logic
Motor starteralso: starter, contactor starter
Equipment that switches motor power on and off. It usually includes protection against excessive motor current.
On site The PLC sends a small run command to a starter, which switches the pump motor's power.
Nalso: N action, non-stored action
A step action active only while its step is active. It stops being active when the sequence leaves that step.
On site The mixer command is active only during the Mix step.
Siemens N action qualifier in GRAPH.Rockwell N action qualifier in SFC.
Taught in: Make every command’s lifetime clear
NOTalso: not operator
Reverses true and false. NOT Stop is true while Stop is inactive.
On site A pump may run only while its fault signal is NOT active.
Siemens NOT in SCL; an inverted contact tests a false operand in LAD.Rockwell NOT in ST; XIO tests a false operand in Ladder.
Taught in: Build permission into the logic
Off-delayalso: off delay, run-on delay
A wait before switching off after a request ends. A new request during the wait keeps the output on.
On site A flushing pump keeps washing a pipe briefly after the wash request ends.
Siemens TOF with IN/PT and Q/ET; SCL uses a TOF_TIME instance here.Rockwell TOF in Ladder; TOFR with TimerEnable/PRE and DN/ACC in ST.
Taught in: Make time explicit
On-delayalso: on delay, start delay
A wait before switching on. The timing request must remain true for the whole wait; removing it starts the wait over.
On site A wash pump ignores a brief button tap but starts after a held request.
Siemens TON with IN/PT and Q/ET; SCL uses a TON_TIME instance here.Rockwell TON in Ladder; TONR with TimerEnable/PRE and DN/ACC in ST.
Taught in: Make time explicit
One-shotalso: one shot, edge pulse
A TRUE pulse lasting one scan when a signal changes. It turns one physical event into one countable request.
On site One bottle under a sensor produces one arrival pulse, rather than a count on every scan.
Siemens R_TRIG/F_TRIG or P/N edge instructions, depending on the language.Rockwell ONS/OSR/OSF in Ladder; OSRI or explicit input-history logic in the supported ST exercises.
Taught in: Count events, not scans
ORalso: or operator
At least one condition must be true. Either condition, or both together, can make the result true.
On site Either Stop or a low-water condition can remove the pump command.
Siemens OR in SCL, parallel paths in LAD and >=1 in FBD.Rockwell OR in ST, parallel branches in Ladder and BOR in FBD.
Taught in: Build permission into the logic
Outputalso: output command
A command sent by the controller to equipment. An ON command does not prove that the equipment moved.
On site A pump command asks its motor starter to supply power to the motor.
Taught in: Know what a tag represents
Permissivealso: permit, permission
A condition that must be satisfied before equipment may run. In these exercises it must also remain satisfied while running.
On site A brewery pump needs enough water in the supply tank before it can run.
Siemens A project condition, often represented by a BOOL such as Permit.Rockwell A project condition, often represented by a BOOL such as Permit.
Taught in: Build permission into the logic
PLCalso: Programmable Logic Controller
An industrial computer that reads inputs, follows your programme and sends commands to equipment.
On site A brewery PLC controls the valves that add water to a mixing tank.
Siemens S7-1500 controllers in this academy; programmed using TIA Portal.Rockwell CompactLogix/ControlLogix controllers in this academy; programmed using Studio 5000 Logix Designer.
Taught in: Think in scans
Presetalso: PT, PRE, PV
The target given to a timer or counter. It says how long to wait or how many events to count.
On site A packing counter has a preset of three bottles before it stops the belt.
Siemens PT is the timer duration; PV is the counter target.Rockwell PRE is the timer or counter preset; timer values here are milliseconds.
Taught in: Make time explicit
Ralso: R action, reset action
An action that clears a command kept on by an S action. Leaving the original step alone does not clear it.
On site The finishing step clears the stored recirculation pump command.
Siemens R action qualifier in GRAPH.Rockwell R action qualifier in SFC.
Taught in: Make every command’s lifetime clear
Rampalso: ramp time, acceleration ramp
The steady rate at which a drive changes speed. It protects the motor, the pump and the pipes from sudden changes.
On site A pump drive takes four seconds to go from stopped to full speed.
Taught in: Ask a drive, then check
Raw valuealso: raw counts, input counts
The number an input card gives the PLC before scaling. It means nothing to an operator until it is converted.
On site A level transmitter's 12 mA arrives as 13824 counts on an S7-1500 input.
Siemens S7-1500 inputs set to 4–20 mA use 0 to 27648 counts for the normal range.Rockwell Logix modules can report raw counts, or scale them to mA or engineering units in the module.
Taught in: From milliamps to a number you can trust
REALalso: real number, floating-point value
A number type that can keep fractional measurements. It has limited precision, so some calculations are approximate.
On site A tank reading of 41.5 percent needs a type that keeps the half percent.
Siemens REAL in the block interface.Rockwell REAL in controller/program tags.
Taught in: Know what a tag represents
Resetalso: reset request
A request to return a value or piece of logic to a chosen starting condition. What it clears depends on the programme.
On site An operator clears the bottle total before counting the next group.
Siemens Counter R input; chart reset and output clearing follow the chart's defined policy.Rockwell Ladder RES or the ST counter Reset member; chart output clearing is a separate programme policy.
Taught in: Count events, not scans
Retentive timeralso: retained timer
A timer that keeps elapsed time when its request stops. A separate reset clears the stored time.
On site A maintenance total can add several separate periods of machine use.
Siemens Retentive timing is a reading topic here, rather than a supported practical timer exercise.Rockwell RTO/RTOR are retentive; TONR in these ST lessons is non-retentive despite its name.
Taught in: Make time explicit
Rising edgealso: positive edge, FALSE-to-TRUE
The moment a signal changes from FALSE to TRUE. A signal held TRUE is not another rising edge.
On site A bottle arriving beneath the sensor creates one rising edge.
Siemens R_TRIG in SCL; P contact or P_TRIG in LAD.Rockwell ONS/OSR in Ladder; OSRI or explicit previous-input logic in ST.
Taught in: Count events, not scans
Rungalso: network
One row of ladder logic containing conditions and an action. Branches can provide alternative paths through that row.
On site One row checks the pump's permission before writing its run command.
Siemens LAD groups are called networks.Rockwell Ladder rows are called rungs.
Taught in: Read a rung
Salso: S action, stored action
A step action that keeps a command on after its step ends. A separate reset action must clear that command.
On site A recirculation pump stays commanded on through a later waiting step.
Siemens S action qualifier in GRAPH.Rockwell S action qualifier in SFC.
Taught in: Make every command’s lifetime clear
SCADAalso: Supervisory Control and Data Acquisition
A site-wide system for watching equipment, readings and alarms. It can record history and let operators make control requests.
On site A water-treatment control room watches several pump stations and their alarms on one system.
Siemens WinCC systems can provide supervisory monitoring.Rockwell FactoryTalk View SE systems can provide supervisory monitoring.
Scalingalso: scale conversion
Turning a sensor's raw number into a useful measurement. The conversion must match the sensor's chosen range.
On site A tank display converts input counts into a level from zero to 100 percent.
Siemens NORM_X then SCALE_X in these exercises.Rockwell SCL with a SCALE backing tag in these exercises; this SCL instruction is not Siemens' programming language.
Taught in: Follow the signal
Scanalso: scan cycle
One pass through reading inputs, running instructions and updating outputs. This academy normally repeats it every 20 milliseconds.
On site While one bottle covers a sensor, the controller can read it many times.
Siemens A cyclic organisation block, such as OB1, repeatedly runs the programme.Rockwell A task schedules routines; these lessons use a periodic task with buffered inputs.
Taught in: Think in scans
SCLalso: Structured Control Language, Siemens SCL
Siemens' text language for writing controller instructions. Local names can start with #, and := writes a value.
On site An engineer writes #PumpOn := #Start to make a pump follow a request.
Siemens SCL routines in TIA Portal.Rockwell The comparable text language is Structured Text; Logix's SCL instruction instead performs analogue scaling.
Taught in: Think in scans
Seal-inalso: seal in, holding circuit, self-hold
A way to remember a brief Start request. The pump stays commanded on until Stop or another stopping condition breaks that memory.
On site A caretaker presses Start once and the water pump keeps running after the button is released.
Siemens LAD parallel holding contact or SCL logic using the previous output.Rockwell Ladder parallel holding branch or ST logic using the previous output.
Taught in: Read a rung
Sensoralso: sensing device
A device that detects or measures something. Its reading tells the controller about the real equipment.
On site A light sensor detects a bottle beneath the filling nozzle.
Taught in: Know what a tag represents
Sequencealso: sequencing
A programme that carries out a job in ordered stages. Each stage has commands and a rule for moving on.
On site A mixing tank fills, mixes its contents and then drains the finished batch.
Siemens GRAPH is Siemens' step-and-transition language.Rockwell SFC is Logix's step-and-transition language.
Taught in: Describe a process in steps
Sequential function chartalso: SFC
A diagram that shows steps of a job and the conditions for changing steps. Actions say what each step does.
On site A filling sequence waits for a bottle, fills it and then moves it onward.
Siemens Siemens GRAPH provides a related sequence language, with its own rules.Rockwell SFC routines in Studio 5000 Logix Designer.
Taught in: Describe a process in steps
Setpointalso: target value
The value you want a process to reach or stay near. It is different from the value currently measured.
On site A wash-water heater aims for a chosen temperature rather than heating forever.
Taught in: Build permission into the logic
Solenoid valvealso: solenoid-operated valve
A valve operated using an electrical coil. The coil can move the valve itself or control air that moves a larger valve.
On site A small electrically operated valve supplies air to the ingredient valve's actuator.
Speed referencealso: speed setpoint, speed command, frequency command
The speed the PLC asks a drive to run at. The drive ramps towards it and reports when it gets there.
On site A pump controller sends its drive 60 percent to slow the flow.
Siemens On a SINAMICS drive, 16384 means 100 percent of the reference speed.Rockwell PowerFlex add-on profiles call it FreqCommand; check its units in the drive manual.
Taught in: Ask a drive, then check
Standbyalso: standby pump, spare pump
Equipment kept ready to take over when the usual unit cannot run. It still needs permission and a usable supply.
On site The spare water pump takes over after the usual pump fails.
Taught in: One request, one eligible pump
State machinealso: state-machine
A programme that remembers which part of a job it is in. It defines commands and permitted changes for each part.
On site A batch can be Running, Held or Complete, with different commands in each state.
Siemens Often written with CASE and a stored state value in SCL.Rockwell Often written with CASE and a state tag in ST.
Taught in: Write one phase as a state machine
Stepalso: sequence step
One part of a sequence that is currently active. It says what to do while waiting for the next change.
On site The Fill step runs the inlet pump and valve until the tank reaches its target level.
Siemens A GRAPH step with assigned actions.Rockwell An SFC step with assigned actions.
Taught in: Describe a process in steps
Structured Textalso: ST, Rockwell ST
A text language for writing controller instructions as statements. IF chooses conditions, and := writes a value.
On site An engineer writes a temperature decision as a short text routine.
Siemens Siemens uses SCL as its text programming language.Rockwell Structured Text routines in Studio 5000 Logix Designer.
Taught in: Think in scans
Tagalso: variable
A name for a value in the programme. Start and PumpOn can name a button request and a pump command.
On site A tank level reading is stored under a name the engineer can watch.
Siemens Local SCL references use #; global data can use named data-block members.Rockwell Tags can be controller-scoped or program-scoped; ST references do not use #.
Taught in: Know what a tag represents
Timeralso: timing instruction
An instruction that measures time against a chosen wait. Its stored values let it follow that wait across many scans.
On site A valve alarm waits briefly so a healthy valve has time to open.
Siemens A declared IEC timer instance, such as TON_TIME.Rockwell TIMER in classic Ladder; FBD_TIMER for the supported ST/FBD timing instructions.
Taught in: Make time explicit
Transitionalso: sequence transition
A condition that allows a sequence to leave one step and enter another. It must become true before the change happens.
On site Reaching the filling target lets the batch move from Fill to Mix.
Siemens Transition condition between GRAPH steps.Rockwell Transition condition between SFC steps.
Taught in: Describe a process in steps
Tripalso: protective trip
A stop caused by a protective device or detected problem. Removing the original request is not necessarily the same as clearing it.
On site A motor's overload protection trips when it draws too much current.
Taught in: Trips, resets and restarts
TRUEalso: true value
A value meaning yes, true or active; FALSE means no or inactive. TRUE on Stop means a stop was requested.
On site The inlet valve receives TRUE when the programme asks it to open.
Taught in: Know what a tag represents
UDTalso: user-defined data type, structure
A named group of different values that belong together. Declaring the group stores information; it does not run equipment by itself.
On site One pump status group holds its running state, start total and measured level.
Siemens A named PLC data type with STRUCT members.Rockwell A User-Defined Data Type used as a tag's type.
Taught in: Data is not executable logic
VFDalso: Variable Frequency Drive, variable-speed drive, VSD, inverter drive
An electronic drive that changes a motor's speed. The controller can request a speed rather than only ON or OFF.
On site A water pump slows down when the building needs less water.
Siemens A drive exchanges commands and status with the PLC; SINAMICS is a Siemens drive family.Rockwell A drive exchanges commands and status with the controller; PowerFlex is a Rockwell drive family.
Taught in: Ask a drive, then check
Wire breakalso: broken wire, open circuit
A cut or loose cable that stops a sensor's signal reaching the PLC. A 4–20 mA input then reads close to 0 mA.
On site A damaged transmitter cable makes the level reading drop far below empty.
Siemens S7-1500 analogue cards can report it as a diagnostic, with the value 32767.Rockwell Logix analogue modules flag it with channel fault status bits.